150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed
Solution:
Let x be the number of days in which 150 workers finish the work.
According to the given information,
150x = 150 + 146 + 142 + ..... (x + 8) terms
Here, 150 + 146 + 142 + ..... (x + 8) terms forms an A.P. with a = 146, d = - 4, n = ( x + 8)
Using the sum of n terms of A.P. formula,
⇒ 150x = (x + 8)/2 [2 (150) + ( x + 8 - 1)(- 4)]
⇒ 150x = (x + 8) [150 + ( x + 7)(- 2)]
⇒ 150x = (x + 8)(150 - 2x - 14)
⇒ 150x = (x + 8)(136 - 2x)
Dividing both sides by 2,
⇒ 75x = (x + 8)(68 - x)
⇒ 75x = 68x - x2 + 544 - 8x
⇒ x2 + 15x - 544 = 0
⇒ x2 + 32x - 17x - 544 = 0
⇒ x (x + 32) - 17 (x + 32) = 0
⇒ (x - 17)(x + 32) = 0
⇒ x = 17, - 32
However, x cannot be negative, hence, x = 17
Therefore, the number of days in which the work was completed is (17 + 8) = 25 days.
Thus, the work was completed in 25 days
NCERT Solutions Class 11 Maths Chapter 9 Exercise ME Question 32
150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed
Solution:
If 150 workers were engaged to finish a job in a certain number of days, 4 workers dropped out on second day, 4 more workers dropped out on third day and so on and if it took 8 more days to finish the work then the number of days in which the work was completed is 25 days
visual curriculum